10/06/2020 Hart Road at US Route 14 Construction Update

October 6, 2020

Roadway paving operations are scheduled to begin tomorrow October7th, for the Hart Road at US Route 14 construction project.  Dailylane closures will occur US Route 14 from Western Avenue to Hart Road and onHart Road, North of Barrington High School to Taylor Avenue.

 

  • October 7 & 8 – Milling Operations on US Route 14     and Hart Road.
  • October 9th – HMA Level Binder on US Route 14
  • October 12th – Longitudinal Joint Sealer on     US Route 14 and Hart Road
  • October 13th – Detector Loop Install on US Route     14
  • October 14th to 16th – HMA     Surface on US Route 14 and Hart Road
  • October 19th – Pavement Marking on US Route 14     and Hart Road