09/18/2020 Hart Road at US Route 14 Construction Update

September 18, 2020

Removal of the Forms of the Retaining Wall at NE Corner of Hart and US Route 14
Completed Median on South Hart

Construction of the Median on South Hart Road

This week, work began on the center median on South Hart Road, sidewalk was installed on both North and South Hart and roadway widening was occurring on US Route 14.

 

Next week, work will begin on the bike path on South Hart and curb and gutter will be placed on US Route 14.