This week, the traffic signals at US Route 14 and Hart Road were activated , Hart Road was opened South of US Route 14, excavation for the shared use path was continuing, landscaping throughout the site was occurring, and construction of the headwall for the culvert that extends under US Route 14 began.
Next week, relocation of the sanitary force main on the North side of US Route 14 will begin and headwall construction on US Route 14 will continue.