This week the asphalt base course was placed on US Route 14, headwall for the 60” elliptical storm sewer was formed, curb and gutter was poured on South Hart Road and pavement removal was completed on North Hart Road. Next week,asphalt paving will be occurring on S. Hart Road and storm sewer will be installed on US Route 14 and North Hart Road.