07/17/2020 Hart Road at US Route 14 Construction Update

July 17, 2020
New Asphalt Pavement on North Hart Road

Forming Concrete Headwall for 60" Elliptical Pipe

This week the asphalt base course was placed on US Route 14, headwall for the 60” elliptical storm sewer was formed, curb and gutter was poured on South Hart Road and pavement removal was completed on North Hart Road.  Next week,asphalt paving will be occurring on S. Hart Road and storm sewer will be installed on US Route 14 and North Hart Road.