04/16/2020 Hart Road at US Route 14 Construction Update

April 17, 2020

This week Union Pacific was on site installing the new railroad signal bungalow.  Excavation was occurring in preparation of boring and installation of a steel casing under the railroad tracks at Hart Road.  The steel casing will house electrical wiring of the US Route 14 and Hart Road traffic signals.  Silt fence was installed throughout the site.  Next week water main relocation work, storm sewer will be installed and pavement patching will be occurring on US Route 14 while earth work will be occurring on Hart Road.  Please be prepared for temporary lane closures and minor traffic delays throughout the week.

 

Excavation for Boring under the RR tracks
Installation of Silt Fence on US Route 14 at Wickstrom Ford